Construction Timeline
4/2
- Slow Test Run
3/21
- Train put on track. 3/15
-Ride is "powered" for first time.
2/6
- Front Tower topped.
2/4
- Station roof starts to go up.
1/3
- Reverse tower starts to raise.
1/2
- Crane arrives at site.
12/19
- First piece of track is
erected.
12/15
- First piece of steel is
erected.
11/20
- Cedar Point announces Wicked
Twister and other 2002 plans.
10/28
- Cedar Point closes for the
season, work continues on footers.
10/19
- Parts of Oceana and Aquarium are
razed, while concrete footers are in the beach.
10/15
- Prep work on removing Oceana
starts. 10/12
- No progress made on "unusual"
work. 10/5
- "Unusual" work starts
by Oceana
9/27
- Cedar Point filled for
building permits.
|