2003 Construction Timeline
       
  • 10/28/2001 - Cedar Point closes for the 2001 season. While most eyes were focused on the construction near Wicked Twister,  marks began to appear near Dodgem's 1.

  • Mid-Nov. 2001 - Dodgem's 1 is removed.

  • April 2, 2002 - Construction starts at the former site of Dodgem's 1.

  • Mid-April 2002- Rock climbing wall is moved across the path, large footers are poured on the site of Dodgem's 1.

  • May 5, 2002 - Cedar Point opens for the 2002 season. A large fence is erected around the Dodgem's site.

  • June 21, 2002 - Several signs appear on the wall/fence surrounding Dodgem's 1. The signs read: "Cedar Point is building for the future, look for news later this season."

  • August 18, 2002 - A construction trailer appears in the site.

  • August 21, 2002 - Track is spotted near Mean Streak, construction slowly starts at Dodgem's site: dirt is moved around, workers check footer's size, etc.

  • August 27, 2002 - Track starts to be stored in Soak City's parking lot, path between construction site and lagoon is closed off, the fence/wall has a opening of a few feet, small clearings begin just south of construction site.

  • August 30, 2002 - majority of south end of the wall/fence is ripped down, construction still cont. quietly in the site.

  • Sept. 3,4,5, and 6, 2002 - Cedar Point removes Troika and Chaos, majority of trees, queues, paths, etc. south of the construction site to the Power Tower area. The lagoons on the construction side are dammed, and are partially filled in.

  • Sept. 9,10,11,12, and 13, 2002 - More clearings continue, several small footers are poured, the ride tower goes vertical to the height of roughly 40 feet.

  • Sept. 21, 2002 - Next leg of tower raises.

  • Sept. 27, 2002 - Individual supports are positioned on footers to create the supports for the 'pull-out;  tower raises up to the next level.

  • Oct. 4, 2002 - Track is hung on the pull-out of the ride; track travels up to the 3rd leg of tower.

  • Oct. 11, 2002 - Supports appear in line with the pull-out of the tower, more track pieces arrive, track is hung on East side of tower(one red piece, one white piece).

  • Oct. 18, 2002 -  Construction on the next leg of tower(4 leg); trench is dug through parking lot from the construction site to the beach.

  • Oct. 25, 2002 - Pullout completes and runs down through a brake run. Numerous small footers are poured near the Power Tower plaza.

  • Nov. 7, 2002 - Track is hung on the small supports near Power Tower plaza - which forms two parallel lines of track.

  • Nov. 12, 2002 - Track on both side of the tower reaches the current top of tower. In a conference call, CEO of Cedar Fair(Cedar Point's parent company), stated the new ride would be announced in the next few weeks.

  • Nov. 15, 2002 - Article appeared in Sandusky Register regarding Cedar Point request to be granted a flood-plain variance for part of the construction for new ride. Full Article (Subscription Required)

  • Nov. 18, 2002 - Next leg of tower is started

  • Nov. 21, 2002 - Cedar Point pulls building permits. Permits show little to no detail except for some financial figures: a hydraulic building is going to cost the park around $200,000 dollars; an electrical building around $40,000, and the ride station at about 450,000 dollars. Footers for the ride are estimated to cost the park one million dollars. Sandusky Register has an article regarding the permits.

  • Nov. 23, 2002 - Cranes receive height extension 

  • Nov. 27, 2002 - Parts of launch track installed 

  • Dec. 5, 2002 - 8th leg of tower is partially constructed.

  • Dec. 13, 2002 - 3:30 PM - The top piece of track is placed on the tower.

  • March 20th - Cars are put on track

  • April 7th - Low power tests begin

  • April 15th - Full power tests begin


April 2: Construction Begins

a


June 21: Sign
a


Aug. 27: Track arrives at parking lot

a


Sept. 13: New ride goes vertical

a


Oct. 11: Track is hung on East side

a


Oct. 27: Pullout